251 2020 - 2020 Inspection (Thermoscan & Detail Condition) for MV Cable & MV Panel 20 kV of Substation 2 & GT Include Grounding Test Gresik
252 2020 - 2020 Installation of New MV Cables & Ladder/Tray from GT to Sub 2 Gresik
253 2020 - 2020 Thermoscan Inspection for Electric Panel Area DIP 2 Gresik
254 2020 - 2020 Thermoscan Inspection for Electric Panel Area DIP 1 Gresik
255 2020 - 2020 Thermoscan Inspection for Electric Panel Area Water Treatment Gresik
256 2020 - 2020 Thermoscan Inspection for Electric Panel Area WWTP Gresik
257 2020 - 2020 Thermoscan Inspection for Electric Panel Area PM3 Gresik
258 2020 - 2020 Thermoscan Inspection for Electric Panel Area HRSG Gresik
259 2020 - 2020 Thermoscan Inspection for Electric Panel Area Demin Gresik
260 2020 - 2020 Thermoscan Inspection for Electric Panel Area Gas Turbine Gresik
261 2020 - 2020 Thermoscan Inspection for Electric Panel Area Coal Boiler Gresik
262 2020 - 2020 Thermoscan Inspection for Electric Panel Area PM1 Gresik
263 2020 - 2020 Thermoscan Inspection for Electric Panel Area SP1 Gresik
264 2020 - 2020 Inspection & Maintenance for MV Motor Panel of DDR SP3 Gresik
265 2020 - 2020 Installation of Ladder & LV Cable for WWTP Feeder Gresik
266 2020 - 2020 Supply and Modification Panel MCC (Additional Component MCC Panel SP PM1) Gresik
267 2020 - 2020 SLO & Electrical Installation on Switchyard 30 MVA & Sub-1 Gresik
268 2020 - 2020 Service & Maintenance ACB 10 unit Gresik
269 2020 - 2020 Service & Maintenance ACB 19 unit Gresik
270 2020 - 2020 Acceptance Test MV Switchgear Probolinggo
271 2020 - 2020 Supply and Installation Grounding WWTP Gresik
272 2020 - 2020 Switchgear Service Contract Gresik
273 2020 - 2020 Supply Skill Man Power of Electrical & Instrument for Maintenance Gresik
274 2020 - 2020 FAT ACB Siemens 3 WL Surabaya
275 2020 - 2020 MCC Inverter 55 kW for Motor 1M-7037 Air Turn Gresik