Our Journey

A Journey of Growth and Expertise

# Duration Project Name Location
1 2018 - 2018 D&E, Cable Route & Grounding Project Pengembangan dan Modernisasi PG Asembagoes Situbondo
2 2018 - 2018 Instalation & Commisioning MV Panel Siemens "NXAIR" Pelabuhan PTSG Tuban Tuban
3 2018 - 2018 Grounding Test (Soil Resistance) Project Pengembangan dan Modernisasi PG Asembagoes Situbondo
4 2018 - 2018 Design Wiring Diagram and Panel Layout For Installation Electric Stadium in Jaya Pura Papua Sidoarjo
5 2018 - 2018 Design Wiring Diagram and Panel Layout For Installation Electric in Tanjung Pura University Sidoarjo
6 2018 - 2018 D&E Instrumentasi and Automation Pendirian Pabrik Garam Halus Segoromadu Gresik
7 2018 - 2018 Installation MV Swtichgear, LV Switchgear, and Bust Dust PJB Payton 9 Probolinggo
8 2018 - 2018 Commissioning Trafo and MV Switchgear Situbondo
9 2018 - 2018 Installation & Commissioning LV Panel Siemens "Sivacon" ER-29 PTSG Tuban Tuban
10 2018 - 2018 Termiantion Fiber Optik Probolinggo
11 2018 - 2018 Installation & Commissioning Battery Charger 110VDC Malang
12 2018 - 2018 Installation Dust Suppression DS-50 Mojokerto
13 2018 - 2018 Commissioning MV Cable & Relay Protection PLT BAGAS Situbondo
14 2018 - 2018 Technical Commissioning Service for MV Motor Slipring 2000 KW Situbondo
15 2018 - 2018 Primary Injection, CT, PT, Metering & Hipot Test for Panel System of Generator 10 MW & 13 MW - PG Asembagoes Situbondo
16 2018 - 2018 Installation CT 20 KV and Current Analisys in Incoming Panel Motor INLINE SHREDDER Situbondo
17 2018 - 2018 Power Quality Analysis of Source Supply Situbondo
18 2018 - 2018 Commissioning LV Panel Situbondo
19 2018 - 2018 ACB Test Of Raisis-Samarinda Samarinda
20 2018 - 2018 Commissioning Siemens SIPROTEC 7UT62 Makasar
Contact Us