# Duration Project Name Location
51 2020 - 2020 Supply Relay Protection Siemens Gresik
52 2020 - 2020 Inspection and Repair MV Cable Gresik
53 2020 - 2020 Dismantling, Installation New Tray, Re-Arrangement Cable Installation Of Panel MCC at WWTP Gresik
54 2020 - 2020 Installation Cable Tray DAF 1 Area Gresik
55 2020 - 2020 Repair Line 1 & 2 Riser Panel of Subs 1 because Short Circuit Fault Gresik
56 2020 - 2020 Installation, Modification Panel Feeder & Power Cable for Compressor PM1 Gresik
57 2020 - 2020 Dismantling & Re‐Installation MV Panel L3 from Sub 1 to Sub 2 Gresik
58 2020 - 2020 Dismantling, Move & Re-Installation Transformer L3 10 MVA from Sub 1 to Sub 2 Gresik
59 2020 - 2020 Enc-Moving Panel and Retrofit Panel Gresik
60 2020 - 2020 Close the Hole of MV, LV & MCC panel Gresik
61 2020 - 2020 Repair MV Cable Sub2-DIP Gresik
62 2020 - 2020 Supply Bucholz Relay Gresik
63 2020 - 2020 Inspection PLC for Area PMT Gresik